Case study: Somerset almshouse air source heat pump installation and general refurbishment

The Almshouse Association’s loan scheme is helping member charities improve and modernise their properties, ensuring they remain comfortable, safe and fit for purpose for generations to come.

A great example is the recent refurbishment of the historic Welch Almshouses in Lamyatt, Somerset. Faced with a substantial programme of essential improvements, the trustees were keen to upgrade the cottages while protecting the charity’s financial reserves. A £25,000 loan from The Almshouse Association helped make this possible, supporting a major refurbishment that included the installation of a new air source heat pump, improved insulation, a replacement kitchen and bathroom, and much more.

The result is a beautifully refurbished home, offering residents greater comfort and a more energy-efficient place to live.

Read how the trustees approached the project, the challenges they faced and how the Association’s loan helped bring their plans to fruition.


Welch Almshouses, Lamyatt

Historical background

Originally built by Christopher Welch in the late 19th Century, for the benefit of ‘agricultural labourers who had resided for not less than five years in the district, who were over 60 years of age and not in receipt of parish relief’, the Welch Almshouse Charity became a Trust by the Will of Christopher Welch in 1916 and has now been housing the poor of the parish of Lamyatt for well over 100 years.  The building is amongst the most eye-catching in the Somerset village of Lamyatt. A pair of Grade II listed stone cottages, built high on a bank with a massive chimney, located on the southern entrance to the village.  

Recent history

It is believed that both properties were fitted with new bathrooms and kitchens in the early 1980s and an oil fired heating system had been installed into number 2, however, there are no records of any other major refurbishment works being carried out to either property. In fact, number 1 was still heated by an open fire with a back boiler.

Records indicate that the almshouses have been continuously occupied with only minor or essential maintenance works carried out.  However, in the summer of 2024, one of the cottages became vacant and the trustees took this opportunity to implement and carry out a significant refurbishment program.

Refurbishment requirement

The trustees had arranged a visit to the recently refurbished Tibberton Almshouses in July 2024 and had been impressed by the scale and quality of the works carried out there.  The visit had given the trustees a good impression of what could be achieved through a well-planned refurbishment. 

It was obvious that to carry out significant refurbishment to the Grade II listed Welch almshouse would require funding and early engagement with the local Conservation Officer, Planning Officer and Council representatives; therefore, these were contacted before any firm plans had been formulated. One local Councillor took the trouble to respond and attended a very informative meeting at the property. However, other officials appeared to be somewhat less engaging. 

The initial refurbishment requirements were based on the Quinquennial survey report of 2022 with further items being identified through site visits.  The resulting list of requirements were further identified as either, ‘essential’, or ‘nice to do’. 

The final refurbishment plan consisted of:

  • Kitchen replacement
  • Bathroom replacement
  • Heating installation
  • Insulation upgrade
  • Flooring replacement
  • Decoration throughout
  • Removal of a very overgrown Eucalyptus tree
  • Minor electrical alterations

Nice to do items included:

  • Upgrade to the leaded windows
  • Stripping of gloss paint from the internal oak doors
  • Providing a wood burner in place of the old open fire
  • Underfloor heating

This list formed the basis for a budget plan, refurbishment outline specification and a critical path analysis.

Some of the minor refurbishment items identified on the list were easily costed and initiated without a detailed specification, but simply with competitive quotations provided by local tradesmen.  For example; removal of the massive Eucalyptus was carried out by Osborne Tree Services Ltd of Castle Cary and the Oak doors were sand blasted (on site) by Alberny Restorations Ltd of Martock.

Click here for a full list of suppliers used and specifications of the work detailed for pricing and clarification

Options for heating and insulation

Agreeing a specification for insulation (including secondary glazing, wall insulation, underfloor and roof insulation) proved to be challenging, as was selection of a suitable heating system. 

Firstly, the building being Grade II listed of stone construction with lime mortar and leaded steel framed windows, did not lend itself to most modern systems of wall and window insulation.  The trustees had difficulty in gaining cohesive advice from many of the contractors approached for quotations. Fortunately, the trustees had some experience and expertise themselves regarding buildings and building services, and were therefore able to discuss the issues fully with the contractors, resulting in a satisfactory, although limited outcome. 

Selection of a suitable heating system was similarly problematical.  It had been suggested that we should consider the installation of an Air Source Heat Pump (ASHP) and the trustees had taken some time with various suppliers and local installers to better understand the implications of such an installation, while simultaneously gaining budget costs for electric storage heating and LPG or oil fired central heating. 

The major concerns with the ASHP installation were;

  • Capability of the system to provide adequate heating in mid-winter
  • The level of building insulation required
  • The operating cost of the system.

The result of these deliberations was that, on balance, considering environmental impact and the availability of Government grants, the ASHP was the preferred option.

Loft insulation had been improved some time ago and was considered to be adequate. However, a satisfactory and suitable system of wall insulation could not be agreed on, therefore the selected insulation improvements consisted of permanently fixed aluminium framed secondary glazing with opening windows and insulation below underfloor heating on the ground floor.

It was considered that removal of the existing coal fire and back burner was essential to the project and the remaining fire opening would either require blocking off, or a new wood burner be provided in the space.  As there were reservations at this time on the potential performance of the ASHP considering the wall insulation issues, it was agreed to provide a wood burner with a new chimney liner. 

Aira UK was selected as the preferred supplier and installer of the ASHP.  Aira UK also provided full designs for the installation, made applications for the Boiler Replacement Scheme Grant and sought planning permission from Somerset Council.

Planning of the work

The initial Critical Path analysis prepared in November 2024, indicated a three-month program with the main works beginning on site in late November 2024 and spread over seven weeks (avoiding the Christmas period) to complete in February 2025 at an estimated refurbishment cost of around £50,000.

Original Critical Path Analysis

Although the Trust felt it could raise the £50,000+ estimated for the full refurbishment, this would leave the Trust with dangerously low reserves. It was therefore agreed to apply for a £25,000 Almshouse Association loan to assist the project.

Relatively minor works, such as removal of the tree, stripping of the doors and the minor electrical works were carried out as the main contractors were being selected.  Kitchen and bathroom fittings and materials were also purchased by the Trust prior to engagement of the fitting contractors.

Early engagement with the Council regarding Listed Building Consent and Planning Permission had not resulted in any advice or concerns being raised, or in fact any communication at all (it was later reported that the communication with the Conservation Officer had been unanswered ‘due to the officer leaving’).  So, when Aira advised us that they could start on site before Christmas, which would have reduced the program considerably, we had no choice but to decline the offer and await a response from the Council.  Further, it seemed highly unlikely that approval would be granted before the second half of February 2025.  

As this created a significant delay, the program was adjusted to move the heating installation to follow the kitchen and bathroom installations and to include the agreed additional works.

Additional works

The trustees agreed to go ahead with providing underfloor heating and insulation to the ground floor areas finished with engineered boards, insulation to the bay window roof, replacement of the aged leadwork and providing a wood burner with chimney liner.

Installation of the chimney liner.    
Tiverton wood burner

The fireplace was removed and a chimney liner fitted by way of a cherry picker at about the extent of its reach, with a new 5kW Tiverton wood burner fitted.

Insulation, underfloor heating.

Underfloor heating, insulation and engineered boards were installed directly onto the existing wooden flooring avoiding any damage to the original flooring.

Progress with the planning application

By the end of March 2025, the majority of the refurbishment works had been completed, including replacement kitchen, bathroom and decorating, leaving only the heating installation, secondary glazing and flooring to be completed. 

However, we had still not received approval from the local planning authority despite repeated requests and there being no objections raised through public consultation or the village planning group. We had, though, received an email from the Planning Officer in early March, advising us that they had now consulted with the Conservation Officer and that

‘[…] the proposal as it stands cannot be supported and the Conservation Officer raises objections to the principle of the proposal. This specifically concerns the installation of the ASHP to the front elevation of Welch Cottage […].’

This was clearly a complete misunderstanding of the application documents as there was no intention of installing the ASHP on the front elevation.  Following our disappointment and frustration at this reply, we forwarded additional drawings and photographs of the intended installation and invited The Planning Officer and Conservation Officer to visit the almshouse to see the works for themselves.  This meeting took place in early May, where the Officers were satisfied with our plans (although there were some further concerns raised regarding the kitchen and bathroom works).

The application was finally approved on 16 July 2025.

Air Source Heat Pump installation

Aira commenced the ASHP installation on 11 August 2025 and completed commissioning on 18 August 2025.

Lessons learned

Despite the many delays to the project, with the resulting ever-lengthening program, the refurbishment remained on budget with no significant compromise on quality being necessary. 

The trustees managed all aspects of the project themselves and would readily recommend all of the contractors involved for future projects. Negotiating the planning and conservation office approval, however, added significant delays and complications to the project. Consideration may be given to the employment of an independent professional Project Manager to relieve this particular pressure on any future refurbishment project.

In conclusion

The Welch Almshouse Charity Trustees invited Lamyatt residents to a ‘Garden Party and open house’ in July 2025 to raise local awareness of the Welch Almshouse Charity and to demonstrate the refurbishments carried out. 

For many villagers it was a cathartic experience in that whilst they had known the building all their lives, they had never before had the opportunity to visit. This was also a useful exercise to promote the recruitment of future trustees.

New beneficiaries moved into the refurbished property in September 2025 and have been impressed by the modern, light and comfortable atmosphere of the refurbished building.

The Trustees of the Welch Almshouse Charity would like to thank The Almshouse Association for making the refurbishment on this scale possible.


The Almshouse Association was delighted to support this project through its grants and loans programme, helping to ensure that another historic almshouse can continue its long tradition of providing homes and communities for those who need them most.

We would like to thank all the people and organisations who so kindly donate to The Almshouse Association and leave gifts in their Wills. Without their generosity, we would not be in a position to help support almshouse charities with their renovations and new builds.

The Almshouse Association awards loans and grants to our member charities every year. In 2025, £1,198,500 was approved in new loans and grants totalled £50,000. Charities pay no interest on the loans, just a small administration fee. As they make repayments on the loans over a ten-year period, the Association can continue to offer loans to charities year after year, meaning that your donations continue to support almshouses and their residents in perpetuity.

If you are interested in making a donation to The Almshouse Association or leaving a gift in your Will, please do visit our Support Us pages here.


posted November 2026